Clerical/Administrative Job Class Study
Project Overview
- Review all clerical, secretarial and administrative positions for correct classification placement and salary range assignment .
|
Primary Project Objectives
- To assure consistency of position allocaiton, current class specifications including minimum qualifications, and proper salary alignment.
- Currently, there are 71 positions allocated to 25 job classifications. It is anticipated that there will be a reduction in the number of overall job classifications.
- To create more career ladders for this series.
|
Follow the progress of the Class Study:
= Completed
= Currently working in this area
u = Not started |
|
Milestone 1 - Project Planning (12/3/07 - 12/11/07)
- HR staff to review classificaitons to identify obvious problems: 12/3/07
- Identify all affected classifications and positions (possible update at a later date).
- Create spreadsheet with Posiiton Description update.
- Send Project Plan to departments for review/comment: 12/3/07
- Comments due back from departments: 12/11/07
- Update Project Plan based on comments received .
|
 |
Milestone 2 - Data Collection (12/17/07 - 1/11/08)
- Project kick-off - HR meets with respective departments and impacted employees to explain project and request updated position descriptions: 12/19/07
- Updated information due back from departments: 1/11/08
|
 |
Milestone 3 - Data Review (1/11/08 - 2/11/08)
- HR meets to develop strategy for reviewing/grouping information.
- Positions reviewed for draft classification and allocation: 1/11/08
- HR staff performs desk audits, as needed.
- Class specifications are updated/created as received.
|
 |
Milestone 4 - Review of Draft Product (2/11/08 - 3/7/08)
- Revised class specifications with tentative position allocations sent to departments indicating initial assessment (without salary range assessment):
2/11/08 2/14/08
- See the first draft of the following documents:
- Comments due back from departments:
2/22/08 3/7/08
- Desk audits performed to clarify information, as needed.
- Update information based on comments, as received.
|
 |
Milestone 5 - Salary Analysis & Final Project (2/11/08 - 3/31/08)
- Begin gathering compensation information for all classifications: 2/11/08
- Complete final memo for distribution: 3/17/08
- Distribute final memo: 3/21/08
- Request any necessary budget documents (P100) from departments: 3/21/08
- Budget documents due back, through Controllers Div.: 3/27 - 3/28/08
- Proposed effective dateof changes: 3/31/08
- Update HR Information System (HR2000) and all PCN files: 3/31/08
- Class specifications abolished as needed.
- See the final documents for the class study:
|
Project Assumptions
- Departments are asked to contact their assigned HR representative* for initial explanation and requests for information
- Discussion will take place about how best to organize and divide the project work.
|
Project Issues
- Project may seem too large and cumbersome due to the large number of positions and classficiations involved in the study.
- Compiling information from many departments may delay Milestone 2.
|
*Department Assignments - HR representatives
| Kelly Mercer |
Rachel O'Brien |
- Administration
- Airport
- Eaglecrest
- Engineering
- Fire
- Public Works
|
- Community Development
- Docks & Harbors
- Finance
- Law
- Parks & Recreation
- Police
|