Taku Dock Reconfiguration

 

Construction Start Date: October 15, 2013

Completion Date: February 15, 2014

Contractor: Trucano Construction

Project Overview: This $0.94 Million project is reconfiguration the CBJ owned Taku Dock to provide space for a second fishing vessel to access the dock to load ice or off load fish. It includes a new concrete deck, second crane pad, HDPE sleived mooring pile and new steel piles. The completion date is February 15, 2014 in order to be ready for the crab season.

 

Plans (Click Here)

 

Project Photos (Click Here)

 

Project Videos (Click Here)

 

Project Contact:

Erich Schaal, Deputy Port Engineer

586-0397

Erich_Schaal@ci.juneau.ak.us

 



CBJ Image
Statter Moorage Schedule 111911