Dimond Park Field #3 Drainage ImprovementsBid Opening Date 10/13/2011| Type of Solicitation: RFQ | Bid/RFP Number: E12-134 | | Date Advertised: October 6, 2011 | Construction Estimate: $14,000 | | Plan Holders List: Current List | Cost of Bid Documents: N/A | Description: The Contractor shall provide all labor, equipment, materials and perform all Work to complete the drainage improvements at the Dimond Park Field #3 in the Mendenhall Valley. | Bid/RFP Documents: Click here to to view documents. | Additional Information:
|
Result | | Low Bidder/Successful Proposer: Cutting Edge Development, Inc. (CDI) | Bid Opening/Proposal Due Date: October 13, 2011 | Bid Amount: $9,400 | Bid/RFP Result Summary: View (PDF) | Award Date: Not Posted | Award Amount: Not Posted | Notice of Award: No Document Posted |