Heron Way Reconstruction and Paving

Project Number: BE19-092Project Manager: Alec Venechuk
Completion Date: August 1, 2019Project Manager Telephone: 907-586-0874
Contract Amount: $$343,806Project Manager Email: alec.venechuk@juneau.org
Contractor:
Southeast Earthmovers, Inc.
Project Location Map: No map posted.
Project Images: Click here for photos.
Description:
This Project consists of reconstruction of Heron Way between both intersections along Wren Drive. The WORK consists of sanitary sewer manhole construction, replacement of the roadway embankment to a depth of 24 inches with shot rock borrow, 2-inch minus shot rock with base course, new asphalt pavement, ditch regrading, new driveway culverts installation, and miscellaneous related WORK.