City and Borough of Juneau
155 S. Seward Street
Juneau, Alaska 99801
tel. 907-586-5240
fax 907-586-5385

Engineering Department

Meander Way Reconstruction

Project Number: E14-091Project Manager: John Nelson
Completion Date: August 31, 2014Project Manager Telephone: 907-586-0896
Contract Amount: $688,376Project Manager Email:
Admiralty Construction Incorporated
Project Location Map: No map posted.
Project Images: No images posted.
This Project consists of reconstruction of Meander Way, from Stephen Richards Drive to about 100 feet beyond Stream Court. The WORK consists of installation of a new underground storm drainage system, sanitary sewer manhole adjustments, an area drain, curb and gutter, valley gutter, replacement of the roadway embankment to a depth of 24 inches, shot rock borrow, 2-inch minus shot rock with base course, new asphalt pavement, a paved sidewalk, and miscellaneous related WORK.


CBJ Image