Pioneer Avenue Reconstruction, Phase III

Bid Opening Date 11/08/2013

Type of Solicitation: BidBid/RFP Number: E14-022
Date Advertised: October 17, 2013Construction Estimate: $1.1 Million
Plan Holders List:
  • Current List
  • Cost of Bid Documents: $50.00
    Description:
    This Project consists of reconstruction of Pioneer Avenue from No. 3151 Pioneer Avenue through the Blueberry Hills Road intersection, the installation of an 8-inch, 10-inch and 16-inch HDPE pipe along Pioneer Avenue and into the Blueberry Hills Road intersection, a temporary 6-inch HDPE water pipe by-pass system, new underground storm drainage and replacement of the street and the right side sidewalk embankments to a 24-inch depth, new asphalt pavement, concrete sidewalks, and curb and gutter
    Bid/RFP Documents:
    Click here to to view documents.
    Additional Information:

    Result

    Low Bidder/Successful Proposer: Arete Construction, Corp.
    Bid Opening/Proposal Due Date:
    November 8, 2013
    Bid Amount:
    $1,034,925.00
    Bid/RFP Result Summary:
    View (PDF)
    Award Date:
    December 23, 2013
    Award Amount:
    $1,034,925.00
    Notice of Award:
    View (PDF)