Summer 2012
Change out Black Bear Chairs to outside pole style
Complete Hooter electrical upgrade
Trail maintenance
Routine summer maintenance

Summer 2011
Mid-Hooter loading station removal
Begin Hooter electrical upgrade
Trail maintenance
Routine summer maintenance

Summer 2010
Porcupine Chair (Beginner Chair)
Hardening of Nordic Trail to Treadwell Ditch

Top of Black Bear Chair - photo by Chris Miller
Summer 2009
Black Bear Chair (Mid-Mountain Chair) - installation of last four towers, upper & lower terminal completed, cable & comm line installed, chairs put on.
Porcupine Chair (Beginner Chair) - check back for updates
Nordic Loop Improvements - project will harden a portion of the Lower Nordic Loop
Ptarmigan Chair - conversion from diesel motor to electric motor. Load testing to be done week of October 26.

Working on the road to the top of Ptarmigan - photo by Jeff Brown
Summer 2008
Road to the Top of the Mountain
Mid-Mountain Chairlift
Beginner Chairlift
Lower Nordic Loop Improvements
Electrical Power to the top of the mountain
|